Environmental Assessment (EA) – Long-Term Waste Management Strategy, Detour Lake Mine
Cambium is partnering with Agnico Eagle Mines Limited to conduct an Environmental Assessment (EA) under Ontario’s Environmental Assessment Act. The goal: address the declining capacity of the landfill at Detour Lake Mine (DLM) in northern Ontario’s District of Cochrane.
Why This Matters
Current landfill: In service since 1983
Remaining capacity: ~55,000 m³ (as of Dec 2022)
Time left: About 8 years
Life of Mine: Projected at 30 years
Needed capacity: Minimum 150,000 m³ to support operations, workforce growth, and mine closure activities
Our Role
Prepared amended Terms of Reference (ToR), approved by the Ministry of the Environment, Conservation and Parks in August 2024
Defined the EA framework, including:
Evaluation of alternative waste management solutions
A robust consultation plan
Engagement & Transparency
The EA process began in December 2024 and includes:
Indigenous community engagement
Local stakeholder consultations
Government agency coordination
Public notices and open houses led by Cambium
The Outcome
Cambium is helping Agnico Eagle develop a sustainable, compliant, and community-informed waste management solution to support the long-term operation of Canada’s largest gold mine.
To find out more: https://ontario.agnicoeagle.com/detour-lake-landfill-expansion/